ENROLLED
Senate Bill No. 759
(By Senator Bowman)
____________



[Passed March 11, 2006; in effect from passage.]
____________
AN ACT to repeal §17-4-17c of the Code of West Virginia, 1931, as
amended; to amend said code by adding thereto a new article,
designated §17-2D-1, §17-2D-2, §17-2D-3, §17-2D-4 and 17-2D-5;
and to amend and reenact §17-4-17b and §17-4-17d, all relating
to construction of highways and bridges; creating the Highway
Design-Build Pilot Program; listing requirements for approval
of design-build projects; requiring monthly progress reports
on design-build projects; requiring annual reports; revising
authority to propose certain rules and requirements;
establishing requirements for issuing invitations for bid;
requiring a report to the legislature; creating procedure for
removal, relocation or adjustment of utility lines or
facilities to accommodate a highway project; requiring notice
of need to remove, relocate or adjust a utility line or
facility; requiring removal, relocation or adjustment plans;
creating liability for not following plan; and requiring
public utility to pay for relocation, removal or adjustment.
Be it enacted by the Legislature of West Virginia:

That §17-4-17c of the Code of West Virginia, 1931, as amended,
be repealed; that said code be amended by adding thereto a new
article, designated §17-2D-1, §17-2D-2, §17-2D-3, §17-2D-4 and §17-
2D-5; and that §17-4-17b and §17-4-17d be amended and reenacted,
all to read as follows:
ARTICLE 2D. HIGHWAY DESIGN-BUILD PILOT PROGRAM.
§17-2D-1. Short title.

This article shall be known and may be cited as the West
Virginia Highway Design-Build Pilot Program.
§17-2D-2. Establishment of a Highway Design-Build Pilot Program.

(a) Notwithstanding any provision of this code to the
contrary, the Commissioner of the West Virginia Division of
Highways may establish a pilot program to expedite the construction
of no more than three special projects by combining the design and
construction elements of a highway or bridge project into a single
contract.

(b) A design-build project may not be let to contract before
the first day of January, two thousand seven, and no more than
three project may be let to contract in the eighteen months
thereafter.

(c) A design-build project may not be let to contract until
the commissioner of the division of highways has established
polices and procedures concerning design-build projects.

(d) After completion of the third project, no projects shall
be commenced unless the West Virginia Legislature either approves
additional projects to further study the effectiveness of the design-build process or makes the program permanent.
§17-2D-3. Invitation for bids.

(a) The division shall prepare an invitation for bids for
pre-qualified design-builders, which must provide at a minimum:

(1) The procedures to be followed for submitting bids and the
procedures for making awards;

(2) The proposed general terms and conditions for the
design-build contract;

(3) The description of the drawings, specifications or other
information to be submitted with the bid, with guidance as to the
form and level of completeness of the drawings, specifications or
submittals that will be acceptable;

(4) A proposed time schedule commencement and completion of
the design-build contract;

(5) Budget limits for the design-build contract, if any;

(6) Requirements or restrictions for the subletting of
specific portions of the design-build contract, if any; and

(7) Requirements for performance bonds, payment bonds,
insurance, professional liability insurance and workers'
compensation coverage.

(b) The division shall make available to the qualified
design-builders, approved subcontractors, suppliers and sureties,
as applicable, additional information including, but not limited
to, surveys, soils reports, drawings or information regarding
existing structures, environmental studies, photographs or
references to public records, or other pertinent information.

(c) The division shall set forth its needs with sufficient clarity to assure that there is a comprehensive understanding of
the project's scope and requirement.
§17-2D-4. Acceptance of design-build bid.

(a) The design-builder shall submit the bid to the division as
required in the invitation for bids.

(b) The design-builder shall furnish a bid bond not to exceed
five percent of the maximum cost of the design-build contract.

(c) The selection committee may choose to reject all bids. If
the selection committee chooses to accept a bid, the committee
shall award the project to the qualified design-builder based on
low bid or a value-based selection process combining technical
qualifications and competitive bidding elements. The selection
committee shall ascertain that the submissions comply with the
requirements of this article and the polices and procedures of the
commissioner.
§17-2D-5. Report to the Legislature.

On or before the first day of December, two thousand eight,
the commissioner shall prepare and submit to the Joint Standing
Committee on Government Organization a report evaluating the
experience of the division of highways with each project, including
whether the division realized any cost or time savings, the number
and cost of change orders, the quality of work performed, the
number of bids received and other issues the commissioner considers
appropriate.
ARTICLE 4. STATE ROAD SYSTEM.
§17-4-17b. Relocation of public utility lines on highway
construction projects.

(a) Whenever the division reasonably determines that any
public utility line or facility located upon, across or under any
portion of a state highway needs to be removed, relocated or
adjusted in order to accommodate a highway project, the division
shall give to the utility sixty (60) days' written notice directing
it to begin the physical removal, relocation or adjustment of such
utility obstruction or interference. If such notice is in
conjunction with a highway improvement project, it will be provided
at the date of advertisement or award. Prior to the notice
directing the physical removal, relocation or adjustment of a
utility line or facility, the utility shall adhere to the
division's utility relocation procedures for public road
improvements which shall include, but not be limited to, the
following:

(1) The division will submit to the utility a letter and a set
of plans for the proposed highway improvement project;

(2) The utility must, within twenty (20) days, submit to the
division a written confirmation acknowledging receipt of the plans
and a declaration of whether or not its facilities are within the
proposed project limits and the extent to which the facilities are
in conflict with the project;

(3) If the utility is adjusting, locating or relocating
facilities or lines from or into the division's right-of-way, the
utility must submit to the division plans showing existing and
proposed locations of utility facilities. These utility plans must
be submitted to the division within thirty (30) days of receipt of
the highways plans or such longer time as may be provided in the letter accompanying the highway plans.

(4) The utility's submission shall include with the plans a
working time analysis demonstrating that the utility adjustment,
location or relocation will be accomplished in a manner and time
frame established by the division's written procedures and
instructions. Such working time plan shall specify the order and
calendar days for removal, relocation or adjustment of the utility
from or within the project site and any staging property
acquisition, compensable work or other special requirements needed
to complete the removal, relocation or adjustment. The division
may approve the work plan, including any requests for compensation,
submitted by a utility for a highway improvement project if it is
submitted within the established schedule and does not adversely
affect the letting date. The division will review the work plan to
ensure compliance with the proposed improvement plans and schedule.

(b) If the utility does not thereafter begin removal within
the time specified in the work plan, the division may give the
utility a final notice directing that such removal shall commence
not later than ten (10) days from the receipt of such final notice.
If the utility does not, within the ten (10) days from receipt of
the final notice, begin to remove or relocate the facility or,
having so begun removal or relocation, thereafter fails to complete
the removal or relocation within the time specified by the work
plan, the division may remove or relocate the same with its own
employees or by employing or contracting for the necessary
engineering, labor, tools, equipment, supervision, materials and
other necessary services to accomplish the removal or relocation, and the expenses of such removal may be paid and collected as
provided at law. If additional utility removal, relocation, or
adjustment work is found necessary after the letting date of the
highway improvement project, the utility shall provide a revised
work plan within thirty (30) calendar days after becoming aware of
such additional work or upon receipt of the division's written
notification advising of such additional work. The utility's
revised work plan shall be reviewed by the division to ensure
compliance with the highway project or improvement.

(c) In addition to the foregoing, the owner of the utility
shall be responsible for and liable to the division or its
contractors for damages resulting from its failure to comply with
the submitted and approved work plan. If the utility owner fails
to provide a work plan or fails to complete the removal,
relocation, or adjustment of its facilities in accordance with the
work plan approved by the division, the owner shall be liable to
the contractor for all delay costs and liquidated damages incurred
by the contractor which are caused by or which grow out of the
failure of the utility owner to provide a work plan or a revised
work plan or to complete its work in accordance with the approved
work plan. The division may withhold approval of permits for
failure of the utility owner to comply with the requirements of
this section.
§17-4-17d. Relocation of public utility lines and public service
districts utility lines on state highway construction
projects.

Whenever the Commissioner of Highways determines that any public utility line owned by a county or municipal governmental
body located upon, across or under any portion of a state highway
needs to be relocated in order to accommodate a highway project for
which proportionate reimbursement of the cost is not available from
any federal program, the commissioner shall notify the public
utility owning or operating the facility which shall relocate the
same in accordance with this section, and the cost of the
relocation shall be paid out of the state road fund.